Network topologyV15
From rollout data to a connected view.
Blue outline: selected site · Red dashed outline: upstream connection blocker · Pale blue halo: assessed FO route. Cross-ring CSG references identify the continuation in the next ring.
Data coverage & review
Topology symbols
Small amber routers at the bottom left show the Capacity value (IOH B1 or IOH POC). Dotted gray connectors indicate this capacity association, not FO progress. Blank Capacity cells have no marker. Town Launch badges show the original P1, P2, P3, or P1P2Ext. value; blank remarks have no badge. Click a cross-ring CSG reference or ring heading to open that ring. Site names appear above the IDs. Site stack: Site ID Surge → Site ID → RAN → site readiness → CSG router → Seq. CSG “NY” / “CSG NY” is displayed as CSG NY Installed (not yet installed). NY RFI means not yet ready for installation; RFI means ready for installation. CSG: Cell Site Gateway. FO: Fiber Optic. ACC: Access Router, per your reference. Router color shows installation/integration progress, not live health.
Reading this topology
Rings are arranged by sequence. Connections follow the Excel Segment field, with each ring in its own lane. Links to other rings end at a labeled CSG reference showing the destination site and ring; repeated CSG symbols represent the same site, not additional sites. Station endpoints represent ACC / Access Routers.
Source & interpretation
Site List Main Data(2).xlsx · 1,141 site records. Multi-endpoint segments are split into consecutive links; each inherits the row’s FO progress and owner. Line labels show FO vendors: CCSI = China Comservice Indonesia, INTISEL = Intisel Prodaktifakom, PJU = Phainan Jaya Utama, BAISELINDO = Baiselindo Asia Network. Click a link for the full vendor name. This is a planning snapshot, not live telemetry.
Huawei integration candidates
Only Huawei sites with Site Status RFI or Installed and Suggestion other than Freeze are included in this menu, its totals, filters and CSV export. NY RFI, Freeze, and already integrated sites are excluded. Path analysis uses the complete network, including upstream sites of other vendors.
Network-ready candidate: RFI / Installed sites qualify through completed FO (“6. Pulling done”, “7. Termination done”, or “8. RFS”) under these rules:
- Direct connection to a Station or Closure.
- Direct connection to a site that is On-Air / Integrated, or has CSG Integrated.
- Direct connection to a candidate qualifying under point 1 or 2.
Point 3 adds one candidate hop only; it does not recursively qualify further sites. Supporting sites may be from any vendor. NY RFI and Freeze sites cannot serve as point 1–2 candidates. Each assessment shows its qualifying point and supporting path.
Ready to schedule: a network-ready candidate whose site is Installed and whose CSG is Installed or Integrated. Other network-ready candidates show the equipment work still needed. This snapshot does not confirm optical tests or commissioning.
| Site | Ring / Sequence | Network path | Equipment status | Next action | Evidence |
|---|